Question: 1/ Work the following using least unit cost heuristics and part period balancing? Holding 2 per week Setup $100 Demand 40, 20, 10, 50, 100,
1/
Work the following using least unit cost heuristics and part period balancing?
Holding 2 per week
Setup $100
Demand 40, 20, 10, 50, 100, 20, 10
2/
What is Kanban? What environments is Kanban effective?