Question: 1. You are providing a status for a 14-week project, which is scheduled to be 50 percent complete at this time. You have completed 9

1. You are providing a status for a 14-week project, which is scheduled to be 50 percent complete at this time. You have completed 9 of the 16 deliverables in this project and spent $1200 of the total project cost of $1900.

What is the Schedule Variance (SV)?

Round your answer to 2 decimal places

2. You are providing a status for a 14-week project, which is scheduled to be 50 percent complete at this time. You have completed 9 of the 16 deliverables in this project and spent $1200 of the total project cost of $1900.

What is the Earned Value (EV)?

Round your answer to 2 decimal places.

3. You are performing an earned value analysis (EVM) on your 28-week project. The project was scheduled to be 50% complete at this time. You have completed 14 of the 32 deliverbles (all of equal value). You have spent $28,000 of your original budget of $48,000.

What is the Earned Value (EV)?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!