Question: 1 You creatAs a project manager, you take time ahead of the project to use effort estimation and capacity planning tools, which will help your
1 You creatAs a project manager, you take time ahead of the project to use effort estimation and capacity planning tools, which will help your team get a realistic sense for how long the project will take. What project plan best practice does this represent? 1 point Giving yourself time to plan Recognizing and planning for the inevitable Championing your plan Staying curiouse a new project plan for your company's staff training program. Which component of the project plan tracks the charter, budget, and RACI chart? 1 point Timeline Milestones Documentation Tasks