Question: 1. You have a construction project and plan to do 20% of the work each week. The project is scheduled to take five weeks and
1. You have a construction project and plan to do 20% of the work each week. The project is scheduled to take five weeks and costs $80,000 in total. After three weeks, 50% of the work has been completed, and $50,000 has been spent. What is the schedule variance for this project? (SV)
A) + $80,000; ahead of schedule
B) + $80,000; behind schedule
C) - $80,000; ahead of schedule
D) - $80,000; behind of schedule
Step by Step Solution
There are 3 Steps involved in it
To calculate the Schedule Variance SV first understand that SV measures the difference between the w... View full answer