Question: 1. You have a construction project and plan to do 20% of the work each week. The project is scheduled to take five weeks and
1. You have a construction project and plan to do 20% of the work each week. The project is scheduled to take five weeks and costs $80,000 in total. After three weeks, 50% of the work has been completed, and $50,000 has been spent. What is the schedule variance for this project? (SV)
A) + $8,000; ahead of schedule
B) + $8,000; behind schedule
C) - $8,000; ahead of schedule
D) - $8,000; behind of schedule
2. Planned project length: 6 months
Time worked to date: 3 months
Project cost (BAC): $120,000
Actual cost (AC): $55,000
Planned percent of project complete: 50%
Actual percent of project complete: 35%
Which of the following statements is True?
A) Project is 20% behind schedule
B) Project is 30% ahead of schedule
C) Schedule variance for this project is negative $18,000
D) Earned value for this project is $9000
3. The customer has a budget of $5,000 for an upcoming IT project which includes:
Software expenses: $200
Operating costs: $500
Service costs: $2500
Calculate the return on investment for this IT project.
A) 25%
B) 42%
C) 36%
D) 10%
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
