Question: 1) You have worked on software development projects in the past and are estimating your current project based on those past experience. What technique are
1) You have worked on software development projects in the past and are estimating your current project based on those past experience. What technique are you using?
a) expert Judgement
b) analagous estimating
c) reverse analysis
d) Three-point estimating
2) You have been assigned as the PM to lead the development of a community dog park. You don't have much experience in this area and you are now tasked with estimating the resources needed. You contact the managers of several dog parks in the region to get their input on how they estimated resources. What technique are you using?
a) bottom-up estimating
b) expert judgement
c) alternative analysis
d) top-down estimating
3) Parametric estimating uses three estimates to generate a weighted average which best represents the overall resource requirement.
a) True
b) False