Question: 10.) For the in-line skate assembly example in this chapter, suppose the times for the individual operations are as follows: Task Time(Sec) 1 20 2

10.) For the in-line skate assembly example in this chapter, suppose the times for the individual operations are as follows:

Task Time(Sec)
1 20
2 10
3 30
4 10
5 30
6 20
7 10
8 20

Assume that inspections cannot be performed by production personnel, but only by persons from quality control. Therefore, assembly operations are separated into three groups for inspection. Design a production line to achieve an output rate of 120 per hour.