Question: 10.) For the in-line skate assembly example in this chapter, suppose the times for the individual operations are as follows: Task Time(Sec) 1 20 2
10.) For the in-line skate assembly example in this chapter, suppose the times for the individual operations are as follows:
| Task | Time(Sec) |
| 1 | 20 |
| 2 | 10 |
| 3 | 30 |
| 4 | 10 |
| 5 | 30 |
| 6 | 20 |
| 7 | 10 |
| 8 | 20 |
Assume that inspections cannot be performed by production personnel, but only by persons from quality control. Therefore, assembly operations are separated into three groups for inspection. Design a production line to achieve an output rate of 120 per hour.