Question: 10 . Question 6 In the table below, EV, AC and PV of the project activities are recorded at the point of monitoring. You are

10 . Question 6 In the table below, EV, AC and PV
10 . Question 6 In the table below, EV, AC and PV of the project activities are recorded at the point of monitoring. You are required to: Make your comments on situation of the project cost and progress? Estimate total project cost at completion (EAC) if the total budget of the baseline (BAC) is 300.000 USD? Unit: 1000 USD Activity EV PV A 50 30 50 B 25 20 15 130 120 100 D 35 60 35 E 0 0 60 F 0 0 0 G 0 0 0 Cumulative Total 240 230 260