Question: . Question 5 In the table below, EV, AC, PV, of the project activities are recorded at the point of monitoring. You are required to:

. Question 5 In the table below, EV, AC, PV, of

. Question 5 In the table below, EV, AC, PV, of the project activities are recorded at the point of monitoring. You are required to: Make your comments on situation of the project cost and progress? Estimate total project cost at completion (EAC) if the total budget of the baseline (BAC) is 600 thousands USD? Unit: 1000 USD Activity EV AC PV A 50 30 50 B 26 20 15 C 130 120 100 D 35 60 35 E 50 42 45 F 36 38 40 G 18 14 15 H 25 28 32 I 62 56 60 J 88 92 80 Cumulative total 520 500 472