Question: 10.11 Project Management: Achieving Competitive Advantage, 5th ed. 10.11 Given the following information, answer the questions about this project: Activity Expected Duration Predecessors A 12

10.11 Project Management: Achieving Competitive Advantage, 5th ed. 10.11 Project Management: Achieving Competitive
10.11 Given the following information, answer the questions about this project: Activity Expected Duration Predecessors A 12 None B 8 None 5 None D 10 A and B E 10 C and D F 5 A and B 1. Draw the network as a Gantt chart. 2. What is the critical path? Which activities have slack time