Question: 11 (1 point) When someone uses experience and/or information from others to determine the project duration and total cost, ____________ estimating is being used. Question

11 (1 point) When someone uses experience and/or information from others to determine the project duration and total cost, ____________ estimating is being used. Question 11 options: top-down experiential bottom-up reference class professional estimation