Question: 11. If __________ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed without jeopardizing completion
11. If __________ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed without jeopardizing completion of the project by its required completion time
a. total time
b. free time
c. total slack
d. critical slack
Step by Step Solution
3.48 Rating (151 Votes )
There are 3 Steps involved in it
c total slack When we talk about the slack of a project we ca... View full answer