Question: 11. If __________ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed without jeopardizing completion

11. If __________ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed without jeopardizing completion of the project by its required completion time

a. total time

b. free time

c. total slack

d. critical slack


Step by Step Solution

3.48 Rating (151 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

c total slack When we talk about the slack of a project we ca... View full answer