11. If __________ is positive, it represents the maximum amount of time that the activities on a...
Fantastic news! We've Found the answer you've been seeking!
Question:
11. If __________ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed without jeopardizing completion of the project by its required completion time
a. total time
b. free time
c. total slack
d. critical slack