Question: 11/26/18 Chapter: 11 Cash Flow Estimation and Risk Analysis Problem: 18 Webmasters.com has developed a powerful new server that would be used for corporations' Internet
| 11/26/18 | ||||||||
| Chapter: | 11 | Cash Flow Estimation and Risk Analysis | ||||||
| Problem: | 18 | |||||||
| Webmasters.com has developed a powerful new server that would be used for corporations' Internet activities.It would cost $10 million at Year 0 to buy the equipment necessary to manufacture the server.The project would require net working capital at the beginning of each year in an amount equal to 10% of the year's projected sales; for example, NWC0= 10%(Sales1). | ||||||||
| The firm believes it could sell 1,000 units per year. The servers would sell for $24,000 per unit, and Webmasters believes that variable costs would amount to $18,000 per unit.After Year 1, the sales price and variable costs will increase at the inflation rate of 3%.The company's nonvariable costs would be $1 million at Year 1 and also would increase at the 3% inflation rate. | ||||||||
| The server project would have a life of 4 years.If the project is undertaken, it must be continued for the entire 4 years. The equipment would be depreciated over a 5-year period, using MACRS rates.The estimated market value of the equipment at the end of the project's 4-year life is $500,000. | ||||||||
| Webmasters' federal-plus-state tax rate is 25%.Its cost of capital is 10% for average-risk projects, defined as projects with a coefficient of variation of NPV between 0.8 and 1.2.Low-risk projects are evaluated with a WACC of 8%, and high-risk projects at 13%. Also, the project's returns are expected to be highly correlated with returns on the firm's other assets. | ||||||||
| a.Develop a spreadsheet model, and use it to find the project's NPV, IRR, and payback. | ||||||||
| Input Data (in thousands of dollars) | ||||||||
| Scenario name | Base Case | Note: the items in red will be used in a scenario analysis. | ||||||
| Probability of scenario | 50% | |||||||
| Equipmentcost | $10,000 | |||||||
| Net operating working capital/Sales | 10% | Key Results: | ||||||
| First year sales (in units) | 1,000 | NPV= | $0 | |||||
| Sales price per unit | $24.00 | IRR = | 0.0% | |||||
| Variable cost per unit (excl. depr.) | $18.00 | Payback = | 0.00 | |||||
| Nonvariable costs (excl. depr.) | $1,000 | |||||||
| Inflation in prices and costs | 3.0% | |||||||
| Estimated salvage value at year 4 | $500 | |||||||
| Depreciation years | Year 1 | Year 2 | Year 3 | Year 4 | ||||
| Depreciation rates | 20.00% | 32.00% | 19.20% | 11.52% | ||||
| Tax rate | 25% | |||||||
| WACC for average-risk projects | 10% | |||||||
| Intermediate Calculations | 0 | 1 | 2 | 3 | 4 | |||
| Units sold | ||||||||
| Sales price per unit (excl. depr.) | ||||||||
| Variable costs per unit (excl. depr.) | ||||||||
| Nonvariable costs (excl. depr.) | ||||||||
| Sales revenue | ||||||||
| Required level of net operating working capital | ||||||||
| Basis for depreciation | ||||||||
| Annual equipment depr. rate | 20.00% | 32.00% | 19.20% | 11.52% | ||||
| Annual depreciation expense | ||||||||
| Ending Bk Val: Cost - Accum Dep'rn | ||||||||
| Salvage value | ||||||||
| Profit (or loss) on salvage | ||||||||
| Tax on profit (or loss) | ||||||||
| Net cash flow due to salvage | ||||||||
| Years | ||||||||
| Cash Flow Forecast | 0 | 1 | 2 | 3 | 4 | |||
| Sales revenue | ||||||||
| Variable costs | ||||||||
| Nonvariable operating costs | ||||||||
| Depreciation (equipment) | ||||||||
| Oper. income before taxes (EBIT) | ||||||||
| Taxes on operating income (40%) | ||||||||
| Net operating profit after taxes | ||||||||
| Add back depreciation | ||||||||
| Equipment purchases | ||||||||
| Cash flow due to change in NOWC | ||||||||
| Net cash flow due to salvage | ||||||||
| Net Cash Flow (Time line of cash flows) | ||||||||
| Key Results:Appraisal of the Proposed Project | ||||||||
| Net Present Value (at 10%) = | ||||||||
| IRR = | ||||||||
| MIRR = | ||||||||
| Payback = | ||||||||
| Discounted Payback = | ||||||||
| Data for Payback Years | Years | |||||||
| 0 | 1 | 2 | 3 | 4 | ||||
| Net cash flow | ||||||||
| Cumulative CF | ||||||||
| Part of year requiredfor payback | ||||||||
| Data for Discounted Payback Years | Years | |||||||
| 0 | 1 | 2 | 3 | 4 | ||||
| Net cash flow | $0 | $0 | $0 | $0 | $0 | |||
| Discounted cash flow | ||||||||
| Cumulative CF | ||||||||
| Part of year required for discounted payback | ||||||||
| b.Now conduct a sensitivity analysis to determine the sensitivity of NPV to changes in the sales price, variable costs per unit, and number of units sold.Set these variables' values at 10% and 20% above and below their base-case values. Include a graph in your analysis. | ||||||||
| % Deviation | 1st YEAR UNIT SALES | Note about data tables.The data in the column input should NOT be input using a cell reference to the column input cell.For example, the base case 1st Year Unit Sales in Cell B100 should be the number 1,000 and NOT have the formula =D31 in that cell.This is because you'll use D31 as the column input cell in the data table and if Excel tries to iteratively replace Cell D31 with the formula =D31 rather than a series of numbers, Excel will calculate the wrong answer.Unfortunately, Excel won't tell you that there is a problem, so you'll just get the wrong values for the data table! | ||||||
| from | Base | NPV | ||||||
| Base Case | 1,000 | $0 | ||||||
| -20% | ||||||||
| -10% | ||||||||
| 0% | ||||||||
| 10% | ||||||||
| 20% | ||||||||
| % Deviation | SALES PRICE | % Deviation | VARIABLE COST | |||||
| from | Base | NPV | from | Base | NPV | |||
| Base Case | $24.00 | $0 | Base Case | $18.00 | $0 | |||
| -20% | -20% | |||||||
| -10% | -10% | |||||||
| 0% | 0% | |||||||
| 10% | 10% | |||||||
| 20% | 20% | |||||||
| Deviation | NPV at Different Deviations from Base | |||||||
| from | Sales | Variable | ||||||
| Base Case | Units Sold | Price | Cost/Unit | |||||
| -20% | $0 | $0 | $0 | |||||
| -10% | $0 | $0 | $0 | |||||
| 0% | $0 | $0 | $0 | |||||
| 10% | $0 | $0 | $0 | |||||
| 20% | $0 | $0 | $0 | |||||
| Range | $0 | $0 | $0 | |||||
d.If the project appears to be more or less risky than an average project, find its risk-adjusted NPV, IRR, and payback.CV range of firm's average-risk project:0.8to1.2Low-risk WACC =8%WACC =10%High-risk WACC =13%Risk-adjusted WACC =Risk adjusted NPV =IRR =Payback =e.On the basis of information in the problem, would you recommend that the project be accepted?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
