Question: 12. Draw the network from the table below, find the critical path, the slack times of the activities, and the minimum cost that Mr James

12. Draw the network from the table below, find the critical path, the slack times of the activities, and the minimum cost that Mr James manage at the NYU by 4 days

Activity Predecessors Normal time (days) Crash time (days) Normal Cost $ Crash Cost $ Crash cost/day
A none 4 3 2000 2600
B none 4 3 2200 2400
C none 14 12 500 600
D A 5 4 2300 2600
E B 8 7 900 1200
F D & E 3 1 1400 1600