Question: 13. Complete the MRP record below. 2 Item: XYZ Description Lot Size: 120 Lead Time: 1 week Date . 2 3 4 . 7 I

13. Complete the MRP record below. 2 Item: XYZ
13. Complete the MRP record below. 2 Item: XYZ Description Lot Size: 120 Lead Time: 1 week Date . 2 3 4 . 7 I 90 40 40 60 20 70 120 Gross Requirements Scheduled Receipts Projected on hand inventory Planned Receipts Planned Order Release 50