Question: 13. Considering this table which activity is critical one? Activities Duration, month Earliest Start A (3-4) 5 6 B (3-5) 3 6 C (3-6) 6

13. Considering this table which activity is

13. Considering this table which activity is critical one? Activities Duration, month Earliest Start A (3-4) 5 6 B (3-5) 3 6 C (3-6) 6 D (3-7) 2 A. C (3-6) B. A (3-4) O C. D (3-7) D. B (3-5) E. None 6 6 Latest Start 6 6 6 6 Earliest Finish 11 13 12 12 Latest Finish 11 19 17 16