Question: Table: Activities Duration, month Earliest Start Latest Start Earliest Finish Latest Finish A (3-4) 11 B (3-5) C (3-6) D (3-7) 13 12 19 17

Table:

Table: Activities Duration, month Earliest Start

Table: Activities Duration, month Earliest Start

Activities Duration, month Earliest Start Latest Start Earliest Finish Latest Finish A (3-4) 11 B (3-5) C (3-6) D (3-7) 13 12 19 17 12 SORU 15 15. Considering table given in question 13, 4 activities may start at the same time. But only two activities could start at the same time at the scheduling day due to the limited resources. Which activities should be postponed? A-) B and D B-) A and C-) A and B D-) A and D E-) Cand D