Question: 13. The following precedence network is used for assembling a product. You have been asked to achieve a daily output rate of 40 units. Assume

13. The following precedence network is used for

13. The following precedence network is used for assembling a product. You have been asked to achieve a daily output rate of 40 units. Assume one day is 8 hours. All times in this network are in minutes. Balance the line using the following rule: assign tasks to workstations on the basis of most following tasks (Rule 1). Use greatest positional weight (Rule 2) as a tiebreaker. What is the irst activity assigned to workstation 4? 3.0 3.0 6.0 b 2.0 7.0 6.0 120 a g 5.0 50 5.0 Ob Og e Od None of the provided options