Question: 13. The following precedence network is used for assembling a product. You have been asked to achieve an output of 240 units per eight-hour day.

13. The following precedence network is used for
13. The following precedence network is used for assembling a product. You have been asked to achieve an output of 240 units per eight-hour day. All times in this network are in minutes. Balance the line using the following rule: assign tasks to workstations on the basis of most following tasks (Rule 1). Use greatest positional weight (Rule 2) as a tiebreaker. What is the utilization (%) of the worker in the workstation 2? 02 04 02 1.2 b a OoQ 0.4 20 10 g e 40 100 30 None of the provided options 50 60 675