Question: #140 What are the three basic elements of project planning? i.Scope ii.Schedule iii.Budget iv.Value stream mapping v.Determining solutions vi.Poka yoke vii.Theory of inventive problem solving

#140

What are the three basic elements of project planning? i.Scope ii.Schedule iii.Budget iv.Value stream mapping v.Determining solutions vi.Poka yoke vii.Theory of inventive problem solving
A i, ii, and iii only
B iv, v, and vi only
C v, vi, and vii only
D ii, vi, and vii only

#139 Design of Experiments may be used with

(Caution: Think it through)

A Continuous level settings
B Discrete level settings
C Neither
D

Both

#138

The central limit theorem:
A Intersects the y axis and becomes the value of y when x = 0.
B The means will be normally distributed regardless of the parent population.
C Separates product-to-product variation and leaves only measurement error.
D

All of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!