Question: Lean Six SIgma Black Belt What are the three basic elements of project planning? i. Scope ii. Schedule iii. Budget iv. Value stream mapping v.

Lean Six SIgma Black Belt What are the threeLean Six SIgma Black Belt

What are the three basic elements of project planning? i. Scope ii. Schedule iii. Budget iv. Value stream mapping v. Determining solutions vi. Poka yoke vii. Theory of inventive problem solving o i, ii, and iii only iv, v, and vi only v, vi, and vii only O ii, vi, and vii only