Question: 1.4.1 Determine the sequence that will minimize the total completion time for these jobs. 1.4.2 Illustrate your optimum sequence in 2.3.1 graphically, showing the throughput

1.4.1 Determine the sequence that will minimize the total completion time for these jobs.
1.4.2 Illustrate your optimum sequence in 2.3.1 graphically, showing the throughput time and idle times on the two workstations.
1.4.3 What is the idle time on Operation 2, given the optimal solution?
b.pdf 12 / 22 10096 1.4 The following eight (8) jobs must be processed through two (2) wo order of workstation one before workstation two. Processing times Job Workstation 1 Workstation 2 (min) (min) 1 13 3 2 2 LO 102 1 3 4 4 6 5 5 7 6 10 5 7 6 10 8 5 5 1.4.1 Determine the sequence that will minimize the total completi these jobs NEStep by Step Solution