Question: .. 14.10 a. Given the product structure and master production schedule (Figure 14.12 Obelow), develop a gross requirements plan for all items. b. Given the


.. 14.10 a. Given the product structure and master production schedule (Figure 14.12 Obelow), develop a gross requirements plan for all items. b. Given the preceding product structure, master production schedule, and inventory status (Figure 14.12 O). develop a net materials requirements (planned order release) for all items. PX Master Production Schedule for X1 PERIOD 7 8 9 10 11 Gross requirements LEAD TIME ITEM LEAD TIME B2 AL Figure 14.12 Information for Problem 14.10 PERIOD 100 5 0 Gross requirements: A Gross requirements: H 150 100 50 ON HAND LEAD TIME ITEM TIM TEM Subassembly LUXUD B11) B22) A1(1) E(1) C(2) D() E12) Given the product structure and master production schedule (Figure 14.12 Obelow), develop a gross requirements plan for all items