Question: 15 Question 15 Based on the chart below, some of the identified risks do not occur and therefore activity B gets done in 3 weeks.
15 Question 15 Based on the chart below, some of the identified risks do not occur and therefore activity B gets done in 3 weeks. What is the effect on the project?
Select one: a. There will be three critical paths. b. The project will complete sooner if activity F starts immediately. c. The project is complete. d. Activity A will have more float.

PM Chart X Activity Preceding Estimate Activity (weeks) Start 0 C Start D C C E D B AE F E End B.F
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock