Question: 16- Activities A,B, and C are the immediate predecessors (preceding activity) for Y activity. If the earliest finishing time for the three activities are 22,25
16- Activities A,B, and C are the immediate predecessors (preceding activity) for Y activity. If the earliest finishing time for the three activities are 22,25 , and 20 , then what will be the earliest starting time for Y ? a) 22 b) Cannot be determined c) 20 d) 25 Leave blank