Question: Activities A , B , and C are the immediate predecessors for Y activity. If the earliest finishing time for the three activities are 1

Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finishing time for the three activities are 13,16, and 11, then what will be the
earliest starting time for Y?