Question: 16) How many logical relationships are possible between two activities? a. 2 b. 4 c. 6 d. 3 17) Developing prototypes to clarify requirements is
16) How many logical relationships are possible between two activities?
a. 2
b. 4
c. 6
d. 3
17) Developing prototypes to clarify requirements is considered which type of strategy for planning risk responses?
a. Transfer
b. Avoid
c. Mitigate
d. Accept
18) You are the project manager for a software project, when the sponsor pulls the plug and cancels the project. What do you do?
a. Give the team the day off to recuperate from the bad news.
b. Create a budget summary for the remaining unspent budget.
c. Follow project closure procedures to close the project and update lessons learned.
d. Find new assignments for any people previously assigned to your project.
19) Communication activities have many potential dimensions that generally include all of the following EXCEPT:
a.
Written, oral, and nonverbal.
b.
Internal and external.
c.
Conceptual and definitive.
d.
Formal and informal.
20)
All of the following statements are true regarding the Plan Scope Management process EXCEPT for which one?
a.
One of the purposes of this process is to create the scope management plan.
b.
One of the purposes of this process is to develop the requirements management plan.
c.
It is the first process in the Project Scope Management Knowledge Area.
d.
You will use facilitated workshops to help develop the outputs of this process.