Question: 16 Question 5 (1 point) Consider a project with following sequence of activities: Activity Predecessor Time (days) B 5 1 D B 10 E AD

16 Question 5 (1 point) Consider a project with
16 Question 5 (1 point) Consider a project with following sequence of activities: Activity Predecessor Time (days) B 5 1 D B 10 E AD 3 F 6 G EF 8 What is the slack of activity A? 0 12