Question: Find the project completion time for the project with following sequence of activities: Activity Predecessor Time A - - - 2 B - - -

Find the project completion time for the project with following sequence of activities:
Activity Predecessor Time
A ---2
B ---5
C ---1
D B 10
E A,D 3
F C 6
G E,F 8