Question: 16.If a SPI is 0.8, then this could be interpreted as 80% by value of work planned to be achieved in the period has been

16.If a SPI is 0.8, then this could be

16.If a SPI is 0.8, then this could be interpreted as 80% by value of work planned to be achieved in the period has been completed: a. True b. False 17. An earned value analysis found that the budgeted cost of work performed (BCWP) = RM16500; budged cost of work scheduled (BCWS) = RM18500; and actual cost of work performed (ACWP) = RM18500. The project condition refers: a. Behind schedule and over-budget b. Behind schedule and under-budget C. Ahead of schedule and over-budget d. Ahead of schedule and under-budget e. None of the above