Question: 17 (4 points For a project, the following earned value data have been assessed: AC: 4,000,000 CV : -500,000 SPI: 1.12 BaC: 9,650,000 What is

17 (4 points For a project, the following earned value data have been assessed: AC: 4,000,000 CV : -500,000 SPI: 1.12 BaC: 9,650,000 What is the earned value of the project? $4,480,000 $3,500,000 $5.650,000 C $3,000,000