Question: 17 Compute the activity variance for the cost where: Planned activity of 631 units. Actual units 635. Cost formula is $1910 per month plus $11
17 Compute the activity variance for the cost where: Planned activity of 631 units. Actual units 635. Cost formula is $1910 per month plus $11 per unit. Actual cost was $9,250. 8 00:30:40