Question: 17.5 points Question 5 Budget Start Week End Week Task1 300,000 1 10 Task2 200,000 1 10 Task3 159,170 1 10 Task4 77,169 1 10

17.5 points

Question 5

  1. Budget Start Week End Week
    Task1 300,000 1 10
    Task2 200,000 1 10
    Task3 159,170 1 10
    Task4 77,169 1 10
    Week1 Week2 Week3 Week4 Week5
    Task1 10% of Budget 10% of Budget 10% of Budget 10% of Budget 10% of Budget
    Task2 10% of Budget 10% of Budget 10% of Budget 15% of Budget 15% of Budget
    Task3 10% of Budget 10% of Budget 10% of Budget 15% of Budget 15% of Budget
    Task4 15% of Budget 15% of Budget 5% of Budget 5% of Budget 5% of Budget

    Week1 Week2 Week3 Week4 Week5
    Task1 8% of Budget 10% of Budget 10% of Budget 15% of Budget 15% of Budget
    Task2 10% of Budget 10% of Budget 10% of Budget 15% of Budget 15% of Budget
    Task3 10% of Budget 10% of Budget 10% of Budget 20% of Budget 20% of Budget
    Task4 20% of Budget 20% of Budget 10% of Budget 10% of Budget 10% of Budget

    Week1 Week2 Week3 Week4 Week5
    Task1 8% of Budget 12% of Budget 14% of Budget 18% of Budget 30% of Budget
    Task2 9% of Budget 10% of Budget 9% of Budget 15% of Budget 14% of Budget
    Task3 10% of Budget 10% of Budget 10% of Budget 20% of Budget 15% of Budget
    Task4 20% of Budget 25% of Budget 15% of Budget 20% of Budget 20% of Budget

    What is CPI of the project at the end of week 2 (CPI accumulated from the beginning of the project)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!