Question: 18. The following precedence network is used for assembling a product you have been asked to achieve an output of 240 units per eight hour

18. The following precedence network is used for
18. The following precedence network is used for assembling a product you have been asked to achieve an output of 240 units per eight hour day. All time in the network are in manutes Balance the line using the following rule assign tasks to worlotations on the basis of most following tades le 1). Use greatest potional with a tietaker, What is the efficiency 02 04 02 12 04 10 20 Select one O a. 90 O b. 76 Oc675 d. None of the provided options ee, 80 2,8333 9.22.5