Question: 18- You have just started working on a project to construct a new toll highway that has been recently approved by the government. You are
18- You have just started working on a project to construct a new toll highway that has been recently approved by the government. You are aware that some local residents are opposed to the construction of the highway and a group of them have been lobbying against it. Some seem to be concerned with the noise from the traffic on the highway, others with the potential that they may need to relocate due to the highway's planned location. Which of the following would be considered valid stakeholders that should be identified and managed in your project?
(1 Point)
Residents of the city
Government employees
Lobbying group
All of the above are stakeholders