Question: (19) 7-c An analyst has observed 28 work cycles, for which the average cycle time was five minutes and the performance rating was 1.05. Allowances

(19) 7-c An analyst has observed 28 work cycles, for which the average cycle time was five minutes and the performance rating was 1.05. Allowances for the department are 25 percent of job time. What standard time is appropriate for this job?

OT= 5minutes, NT=5.25 minutes, PR =1.05, ST=6.5625 minutes, A=25%, AFjob=1.25

Group of answer choices

ST = OT x PR

ST= OT x AFjob

ST =PR x AFjob

ST = OT x PR x AFjob