Question: 19. The critical path in a PERT chart represents the A) sequence of operations that involves outside suppliers B) sequence of operations that requires the


19. The critical path in a PERT chart represents the A) sequence of operations that involves outside suppliers B) sequence of operations that requires the longest time for completion C) areas of operations that require the least amount of technical support D) areas of operations that have abundant and extra time