Question: 19. The following data pertain to operations at Quick Incorporated: Throughput time 6.8 hours Delivery cycle time 13.6 hours Process time 1.7 hour Queue time
19.
The following data pertain to operations at Quick Incorporated:
| Throughput time | 6.8 | hours | |
| Delivery cycle time | 13.6 | hours | |
| Process time | 1.7 | hour | |
| Queue time | 3.4 | hours | |
|
| |||
The manufacturing cycle efficiency (MCE) for this operation would be:
12.5%
25.0%
75.0%
50.0%