Question: 19 . We know that in Week 1, there are 20 ABCs in stock (i.e., 20 units of product ABC as on-hand inventory). We also
19. We know that in Week 1, there are 20 ABCs in stock (i.e., 20 units of product ABC as on-hand inventory). We also know that there are scheduled receipts planned for week 3 and week 4 of 120 ABCs in each of these weeks. We also know that this product ABC has a lead time of 1 week. When and how large of an order should be placed (i.e., planned order release) to meet the gross requirement of 340 ABCs in week 5? Note: There are no other Gross Requirements in the other weeks.
- Week 4, 90 units of ABC
- Week 3, 30 units of ABC
- Week 3, 90 units of ABC
- Week 4, 40 units of ABC
- None of the above