Question: 1a. An analyst has timed a metal-cutting task for 50 cycles. The average time per cycle was 10.40 minutes, and the standard deviation was 1.20
1a. An analyst has timed a metal-cutting task for 50 cycles. The average time per cycle was 10.40 minutes, and the standard deviation was 1.20 minutes for a worker with a performance rating of 125 percent. Assume an allowance of 16% of task time. Calculate the standard time for this task (10%) 1b. A task was timed for 60 cycles. It took an average of 1.2 minutes per cycle. The performance rating was 95%, and workday allowance is 10%. Determine each of the following: obse1a. An analyst has timed a metal-cutting task for 50 cycles. The average time per cycle was 10.40 minutes, and the standard deviation was 1.20 minutes for a worker with a performance rating of 125 percent. Assume an allowance of 16% of task time.
Calculate the standard time for this task (10%)
1b. A task was timed for 60 cycles. It took an average of 1.2 minutes per cycle. The performance rating was 95%, and workday allowance is 10%.
Determine each of the following: (10 Points)
a. Observed time.
b. Normal time.
c. Standard time.

1a. An analyst has timed a metal-cutting task for 50 cycles. The average time per cycle was 10.40 minutes, and the standard deviation was 1.20 minutes for a worker with a performance rating of 125 percent. Assume an allowance of 16% of task time. Calculate the standard time for this task (10%) 1b. A task was timed for 60 cycles. It took an average of 1.2 minutes per cycle. The performance rating was 95%, and workday allowance is 10% Determine each of the following: (10 Points) a. Observed time. b. Normal time. c. Standard time
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts