Question: An analyst has timed a metal - cutting task for 5 0 cycles. The average time per cycle was 1 1 . 7 minutes, and

An analyst has timed a metal-cutting task for 50 cycles. The average time per cycle was 11.7 minutes, and the standard deviation was 1.34 minutes for a worker with a performance rating of 120 percent. Assume an allowance of 15 percent of task time. Calculate the standard time for this task.