Question: 1a) If the NPV for a project is +400, using a discount rate(cost of capital) of 14%, then the IRR for the project must be:
1a) If the NPV for a project is +400, using a discount rate(cost of capital) of 14%, then the IRR for the project must be:
|
| Less than 14% |
|
| Equal to 14% |
|
| Greater than 14% |
|
| None of the above |
Question 1b)
Given the graph shown, and a crossover rate of 8%, assume the projects are mutually exclusive,(can only pick a single project), at a cost of capital of 5% which project would NPV CHOOSE(1ST ANSWER), which project would IRR CHOOSE(2nd answer)
|
| A, B |
|
| B,A |
|
| B,B |
|
| A,A |
Question 1c)
You are considering the following 2 mutually exclusive projects. Using the equivalent annual annuity method and a cost of capital of 10%, which project should be selected. (Round to nearest $)
|
| Project A | Project B | ||
| Year | Cash Flow | Cash Flow | ||
| 0 | (20,000) | (20,000) | ||
| 1 | 15,000 | 5,000 | ||
| 2 | 20,000 | 10,000 | ||
| 3 |
| 15,000 | ||
| 4 |
| 50,000 | ||
|
|
|
| ||
|
| Project B because of an EAA of $12,060 | |||
|
| Project A because of an EAA of $5,857 |
|
| Project B because of an EAA of $38,320 |
|
| Project A because of an EAA of $10,165 |
Question 1d)
The internal rate of return is the rate of interest that makes the present value of a projects cash inflows:
|
| greater than the present value of its cash outflows |
|
| less than the present value of its cash outflows |
|
| equal to the present value of its cash outflows |
|
| none of the above |
Question 1e)
Equity is historically much riskier than ___________________________.
|
| Debt |
|
| NPV |
|
| Interest Rates |
|
| none of the above |
Question 1f)
Although quick and easy to apply, the payback method is deficient in that it
|
| disregards the time value of money |
|
| is based on arithmetic rather than algebra |
|
| disregards cash flows after the payback period |
|
| a and c |
Question 1g)
You are considering the following 2 mutually exclusive projects. Using the equivalent annual annuity method and a cost of capital of 10%, which project should be selected. (Round to nearest $)
|
| Project A | Project B | ||
| Year | Cash Flow | Cash Flow | ||
| 0 | (20,000) | (20,000) | ||
| 1 | 15,000 | 5,000 | ||
| 2 | 20,000 | 10,000 | ||
| 3 |
| 15,000 | ||
| 4 |
| 50,000 | ||
|
|
|
| ||
|
| Project B because of an EAA of $12,060 | |||
|
| Project A because of an EAA of $5,857 |
|
| Project B because of an EAA of $38,320 |
|
| Project A because of an EAA of $10,165 |
Question 1h)
Project A has annual cash flows of $200.00 for the next three years. Project B has annual cash flows of $100.00 for the next three years and then annual cash flows of $500.00 for the following four years. Assuming both projects have an initial cost of $500.00, which project is better based on the payback period criteria?
|
| Project A |
|
| Project B |
|
| Cannot be determined without discount rates for each project |
|
| Both projects have the same payback period |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
