Question: 1.A manufacturing process has five sequential workstations that have process times of 14,30,12,30, and 28. What is the bottleneck time? a.114 b.60 c.29 d.30 e.12
1.A manufacturing process has five sequential workstations that have process times of 14,30,12,30, and 28. What is the bottleneck time?
a.114
b.60
c.29
d.30
e.12