Question: 1a). PV (Planned Value) You are managing a project that is expected to take 12 months, and the expenses are budgeted to be $19000 per
1a). PV (Planned Value)
You are managing a project that is expected to take 12 months, and the expenses are budgeted to be $19000 per month. 3 months after the project started, you find out that the project is 10% complete and that you have spent $10000.
What is the PV for this project?
1b). SV (Schedule Variance)
You are managing a project that is expected to take 10 months, and the expenses are budgeted to be $8000 per month. 5 months after the project started, you find out that the project is 80% complete and that you have spent $11000.
What is the SV (Schedule Variance) of the project at this point?
1c). CPI (Cost Performance Index)
You are managing a project that is expected to take 9 months, and the expenses are budgeted to be $5000 per month. 7 months after the project started, you find out that the project is 80% complete and that you have spent $17000.
What is the CPI (Cost Performance Index) of the project at this point?
1d). SPI (Schedule Performance Index)
You are managing a project that is expected to take 10 months, and the expenses are budgeted to be $1000 per month. 7 months after the project started, you find out that the project is 20% complete and that you have spent $13500.
What is the SPI (Schedule Performance Index) of the project at this point?
1e). EAC (Estimate at Completion)
You are managing a project that is expected to take 11 months, and the expenses are budgeted to be $1500 per month. 7 months after the project started, you find out that the project is 20% complete and that you have spent $20000.
What is the EAC (Estimate at Completion) of the project at this point?
1f). ETC (Estimate to Complete)
You are managing a project that is expected to take 8 months, and the expenses are budgeted to be $19000 per month. 2 months after the project started, you find out that the project is 40% complete and that you have spent $11000.
What is the ETC (Estimate to Complete) of the project at this point?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
