Question: 1.Arrows on an activity-on-node (AON) project network represent. Single choice. (1 Point) An activity Project flow Dependency Project flow and dependency 2.Activities which can take
1.Arrows on an activity-on-node (AON) project network represent. Single choice.
(1 Point)
An activity
Project flow
Dependency
Project flow and dependency
2.Activities which can take place at the same time are termed. Single choice.
(1 Point)
Parallel Activity
Burst Activity
Merge Activity
3.Lags can be used to constrain the start and finish of an activity. Single choice.
(1 Point)
True
False
4.The critical path in a project network is the. Single choice.
(1 Point)
Shortest path through the network
Longest path through the network
Network path with the most difficult activities
5.A(n) _________ activity has more than one dependency arrow flowing from it. Single choice.
(1 Point)
Parallel
Critical path
Burst
Merge
6.Which of the following can be used without coordinating with managers of succeeding activities?. Single choice.
(1 Point)
Total Slack
Free Slack
Critical Float
7.Information to develop a project network is collected from the. Single choice.
(1 Point)
Organization breakdown structure
Work breakdown structure
Budget
Project proposal
8.Using free slack does not delay any following activities and requires no coordination with managers of other activities. Single choice.
(1 Point)
True
False
9.If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?. Single choice.
(1 Point)
Check to see which activities cost the least
Check to see which activities have the longest duration
Check to see which activities are on the critical path
10.The minimum amount of time a dependent activity must be delayed to begin or end is referred to as. Single choice.
(1 Point)
Hammock
Laddering
Lag