Question: 1.Based on the PMI framework, what 2 steps should take place before others in the life of a project? A.build the project management plan and
1.Based on the PMI framework, what 2 steps should take place before others in the life of a project?
A.build the project management plan and document the scope
B.write the project charter and document the needs assessment
C.stakeholder identification and requirements documentation
D.identify stakeholders and develop the project charter
2. A document that contains a list of project stakeholders and characteristics of each is:
A.The stakeholder directory
B.The stakeholder dictionary
C.The stakeholder register
D.The stakeholder analysis
3. Which statement is not true regarding the strategy of managing project stakeholders?
A.The management strategy for project stakeholders should be accessible to the project team so they will know how to handle the stakeholders.
B.The stakeholder register is considered a project document.
C. A project onlooker that has enough influence to hurt your project should prompt you as the PM to create a mitigation plan.
D. A sponsor's advocate in senior management should be kept notified of the key aspects of the project to maximize his support in management meetings.
4.What is the name of the tool or technique used for stakeholder identification that adds a third dimension to the traditional grid of power and interest?
A.Stakeholder impact matrix
B.Power, interest, influence grid
C.Power, influence, impact grid
D.Stakeholder cube
5.The team member asked if he could email the stakeholder register to the customer point of contact, and the project manager advised against it. The PM said some of the information in the stakeholder register should not be shared outside the team. What valid element of the stakeholder register would cause concern?
A.assessment information
B.stakeholder classification
C.location and contact
D.phone number role on the project