Question: 1.Create a WBS using Figure 9.3 as an example. 2. Create a network diagram using Figure 10.1 in the Verzuh text as an example. 3.Create

1.Create a WBS using Figure 9.3 as an example.

2. Create a network diagram using Figure 10.1 in the Verzuh text as an example.

3.Create work packages using Tables 10.1 10.5 in the Verzuh text as examples.

TABLE 10.1 Home Landscape Project Work Package Estimates
ID Task Name Duration Labor Hours Resource Names
1 Design home landscape 5 days 80 hrs. Homeowner [0.5], Teens [1.5]*
2 Put in lawn
3 Acquire lawn materials 2 days 64 hrs. Homeowner, Teens [3]
4 Install sprinkler system
5 Identify sprinkler locations 1 day Fixed fee, 8 hrs. Contractor, Homeowner
6 Dig trenches 2 days Fixed fee Contractor
7 Install pipe and hardware 3 days Fixed fee Contractor
8 Cover sprinkler system 1 day Fixed fee Contractor
9 Plant grass
10 Remove debris 4 days 256 hrs. Teens [3], Youth Group [5]
11 Prepare soil 4 days 96 hrs. Teens [3], Rototiller
12 Plant lawn seed 1 day 16 hrs. Teens [2]
13 Plant shrubs 6 days 96 hrs. Teens [2]
14 Build fence
15 Acquire fence material 2 days 16 hrs. Homeowner
16 Install fence
17 Mark fence line 1 day 32 hrs. Homeowner, Teens [3]
18 Install posts 5 days 80 hrs. Teens [2]
19 Install fencing and gates 6 days 144 hrs. Teens [3]
20 Paint/stain fence and gates 3 days 72 hrs. Teens [3]
TABLE 10.2 Work Package Estimate: Example 1
Task description: During an environmental study, a power company counts salmon during a 40day salmon run.
Assumption: The federal agency overseeing the power company dictates the length of the study.
Duration: 40 days Materials: None
Labor and Equipment Table
Type Average Use Total
Salmon Specialist 1 @ 10 hrs./day 400 hrs.
Field Technician 2 @ 10 hrs./day 800 hrs.
Truck 1 all day 40 days
Increasing the number of people on this task does not change the duration but it could increase the accuracy of the study.
TABLE 10.3 Work Package Estimates: Example 2
Task description: During a training project, software is upgraded on 20 workstations in a training room.
Assumption: The average time to install the software is 2 hours per workstation. Testing is 1 hour per workstation. Only one person can work on one workstation at a time.
First Estimate
Duration: 5 days Materials: 20 copies of the new software
Labor and Equipment Table
Type Average Use Total
Computer technician 1 @ 8 hrs./day 40 hrs.
Tester (user or technician) 1 @ 4 hrs./day 20 hrs.
Software test kit 1 per tester 1 test kit
The training manager does not want the training room out of use for a whole week. In fact, he wants the upgrade done over a weekend so the training room doesn't lose any availability.
Revised Estimate
Duration: 2 days Materials: 20 copies of the new software
Labor and Equipment Table
Type Average Use Total
Computer technician 2 @ 10 hrs./day 40 hrs.
Tester (user or technician) 1 @ 10 hrs./day 20 hrs.
Software test kit 1 per tester 1 test kit
By adding 1 computer technician and working longer days, the duration is cut from 5 days to 2.
TABLE 10.4 Work Package Estimates: Example 3
Task description: A government agency is mapping a forest. Aerial photography of the entire area is the first step in creating the maps.
Assumption: An aerial photography subcontractor rents airplanes (complete with pilots and photographers). The agency has one scientist ride with every airplane. The forest is broken into 60 squares. They can photograph one square per day. During the flight, a ground technician stays in radio contact with the scientist to answer mapping questions.
First Estimate
Duration: 60 days Materials: None
Labor and Equipment Table
Type Average Use Total
Scientist (in plane) 1 @ 8 hrs./day 480 hrs.
Airplane 1 @ 8 hrs./day 480 hrs.
Ground technician 1 @ 8 hrs./day 480 hrs.
The forest area traditionally has so much cloudy weather that the agency estimates there will be only one clear day out of every three, but the photography needs to take place during the three months of summer when there is no snow.
Given this requirement, they decide to fly two airplanes every clear day. On days they can't fly there is no airplane cost and the scientist and ground technician can work on other things. A single ground technician can stay in contact with both airplanes.
Revised Estimate
Duration: 90 days Materials: None
Labor and Equipment Table
Type Average Use Total
Scientist (in plane) 2 @ 2.7 hrs./day 480 hrs.
Airplane 2 @ 2.7 hrs./day 480 hrs.
Ground technician 1 @ 2.7 hrs./day 480 hrs.
Since one ground technician can talk to both airplanes, the total labor for that person is cut in half. The expected hours for the scientist and the airplanes stay the same.
The average use estimates are used during the resourceleveling step to indicate the average amount of time the scientists and ground technician will have available to work on other projects during this 90day period.
TABLE 10.5 Work Package Estimates: Example 4
Task description: A systems analyst is working on three projects at the same time. One of her project managers asks her to estimate the design of a subsystem.
Assumption: She will continue to work on all three projects simultaneously.
First Estimate
Duration: 40 days Materials: None
Labor and Equipment Table
Type Average Use Total
Systems analyst 1 @ 2.5 hrs./day 100
Her project manager needs the design performed much faster and suggests he could get another analyst to work with her parttime.
Revised Estimate
Duration: 30 days Materials: None
Labor and Equipment Table
Type Average Use Total
Systems analyst 2 @ 2.5 hrs./day 150
Adding people to a design task can speed up some of the work, but much of it will be done together so it results in an increase in the total labor cost. It is possible the resulting design will be better, but that is another assumption.
Then the project manager asks her what it would take to get it done the fastest. She responds, Talk to my other project managers and arrange to get me completely off those projects for a few weeks so I can concentrate 100 percent on yours.
Revised Estimate
Duration: 10 days Materials: None
Labor and Equipment Table
Type Average Use Total
Systems analyst 1 @ 2.5 hrs./day 80
Not only is she able to spend more time per day on this task but she knows that if she is able to concentrate on it 100 percent she will be more productive.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!