Question: 1.If your project has some repetitive processes, you can take samples at various times to identify trends and manage the quality level. To makes sure

1.If your project has some repetitive processes, you can take samples at various times to identify trends and manage the quality level. To makes sure that the processes/products stay within acceptable limits you would use a _______________."

control chart

cause-effect diagram

fishbone diagram

Pareto chart

2. Demming's cycle proved the concept that a well run quality program would create more savings for a company than the cost of its implementation.

True

False