Question: 1.Prepare a Network Diagram - Activity on Node (AON) 2.Complete the forward and backward pass to determine early start, early finish, late start, and late

1.Prepare a Network Diagram - Activity on Node (AON)
2.Complete the forward and backward pass to determine early start, early finish, late start, and late finish dates and slack for each activity.
3.What is the Critical Path for this project?
4.What is the completion date for this project?
EXHIBIT 1: ACTIVITIES TO COMPLETE PLANT RELOCATION-AFTER ARCHITECTURAL DESIGN AND PLANT LAYOUT COMPLETED Source: Company files
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
