Question: 1.Suppose you have a three task sequence. All customers go to Task A. After task A, 25% of customers go to Task B; the other
1.Suppose you have a three task sequence. All customers go to Task A. After task A, 25% of customers go to Task B; the other 75% go to task C. After task B or C, all customers then go to Task D before leaving. No buffers exist between tasks, so blocking/starvation rules apply.
Suppose throughput capacities are as follows. Task A: 10 customers/hour; task B: 5 customers/hour; task C: 6 customers/hour; task D, 9 customers/hour.
At what rate will customers leave task D (in customers/hour)? Assume the 25%/75% split between tasks B & C must always be upheld.
Pick the closest answer.
5
6
7
8
9
10
2.Following the previous 2 questions, what is the bottleneck in the A-C-D process route?
A
B
C
D
E
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
